Products
The table form is a large beam system devised to install integrated joists, sleepers and floor slabs by vertical and horizontal movement and assembly. Since slab form is installed, dismantled, lifted and reinstalled using equipment, the table form can shorten the time needed for work and reduce labor costs. Table forms are mainly used to reduce the length of work needed for skyscrapers.
Move electronic forklift and lifting device under table form. Drop to a designated height. Move by electronic forklift.
Place table form on lifting rail. Push out of building and lift to higher floor for installation.
Place table form at designate position. Support staging under table form. Place form on joint to complete beam and slab form.
The multi-lifting jig is for methods in which the table form or beam form is preassembled on the ground and moved to and installed at the designated place through lifting by a tower crane. While the tower crane lifts one set of forms at a time, a multi-lifting jig can lift and move 4 to 5 sets at once. Lifting ropes of multi-lifting jig use different colors by level for classification purposes.